Installation and commissioning of jaw crusher

SAMSUNG DIGITAL CAMERA

1. The jaw crusher need to install in place of shelter, outdoor place.
2. The jaw crusher machine should be installed in the rear of the jaw crusher, direction of rotation must be done by the requirement, not reverse.
3. The machine should be firmly fixed in the concrete, the foundation to set aside trough, the slope is not less than 50 degrees.
4. Before the adjustment of mandibles crusher pie mouth, should loosen the tension spring, after being adjusted, in the appropriate adjust the spring tension, spring tension to can eliminate noise between the bracket and the bracket pad and bracket on the job is not easy to fall off.
5. With the jaw crusher and other crushing equipment and management, is conducive to production, be helpful for assembly line work, guarantee the working face no congestion.
6. To raw material product easy to transport, front-rear had better use mechanized transport equipment.
7. Jaw crusher before commissioning tighten the screws and the connecting parts, check the lubrication condition.
8. Use human lift pulley, first confirmed after an unimpeded, run-in test, can be made within two hours can not have shock, noise, and swing pulley and shaft seal leakage between the phenomenon such as loose. Bearing temperature rise not to exceed 35 degrees, if discover fault must immediately stop check.
9. A user load test need to ten hours, and USES the hard ore.