Cone crusher operation steps


The correct cone crusher operation steps are as follows:
1. The cone crusher before starting, check the lubrication system, the broken area of the cone crusher, correction of belt tensioning degree, check whether screw fastening.
2. Cone crusher to start the oil pump motor 5-10 minutes later, check the work condition of lubrication system, oil pressure can start, when the normal cone broken main motor.
3. When the motor for crushing the cone cone for maintenance, check the contact of the cone crusher shaft with taper sleeve wear situation, if more than 3 mm gap or found a crack in the spindle spindle should be timely replacement.
4. The cone crusher empty load operation after 1-2 minutes can begin to mine. For coarse crushing type cone crusher, general can full feed, need not worry. In type of finely cone crusher, we want to ensure the feed speed, not too hard. There is more material moisture, hardness, make effective clearance cycle to ensure material does not adhere to the crushing cavity wall.
5. For dynamic cone block ore body under the part of some, if wear more than ring high 1/2 should repair welding when the steel plate.
6. Normal shutdown, should first stop feeding, after being ore all out of cone crusher, to stop the main motor running. The final stop the oil pump motor. After parking to overall check various parts of the crusher, found that the problem should be handled in a timely manner.
7. Spherical cone crusher body wear more than 4 mm, or the lower cone body contact with the lining board of wear more than 4 mm, the body should be replaced.

Machinery in use process will produce a certain degree of wear and tear, so, we should correct operation, to avoid unnecessary damage. If you are interested in cone crusher, welcome to consult customer service, online 24 hours a day.