For a small sand and gravel plant, investing in an 80-ton gravel production line can meet basic production needs and bring considerable benefits. So, what costs are needed to build this production line? Is there any reference process? Please see below.
1. Costs required to build an 80-ton gravel production line
The cost includes equipment, procedures, site, labor and others. Due to the small scale, only two or three equipment are needed, and the cost is not high, starting from about hundreds of thousands, but other costs are related to regional consumption, regulations, etc., and there is no specific data. Please contact us for detailed quotations and customized solutions.
2. Detailed explanation of the process flow of the 80-ton gravel production line
The ore enters the silo, is fed into the jaw crusher by the feeder to be processed into stones below 60 cm, and then is sent to the medium crusher by the conveyor to be processed into 5-60 mm stones, and the vibrating screen is used to select the finished products. Some lines are equipped with vibrating screens to check the size of the stone to prevent blocking.
Scheme 1—Applicable to low-hardness materials
Configuration: jaw crusher + impact crusher + auxiliary equipment
Features: stable operation, multiple finished product specifications, and good particle shape
Solution 2—Applicable to high-hardness materials
Configuration: jaw crusher + cone crusher + auxiliary equipment
Features: strong crushing force, good wear resistance, strong controllability.
3. Selection of stone crushing line equipment manufacturers
There are many manufacturers with varying quality, so choose carefully. It is recommended to visit the factory or the operation site to ensure quality.